DEMOLITION TURBIDITY CONTROL
2016-2017
Challenges:
-
Turbidity NTE 30% increase
-
Deep water, significant currents
-
Buried obstructions precluded sheet pile
-
Silt curtain not effective enough
-
Pressing project schedule
Solutions:
-
Bottom-sealing filter barriers
-
Designed to perform for the 6-month project schedule, allowing for cost-saving design elements
-
Responsive to schedule needs
Outcome:
-
No project exceedances
-
In-water maintenance allowed performance to continue for an unplanned extension from 6 to 18 months
-
Bulky underwater debris complications addressed without compromise in performance