DEMOLITION TURBIDITY CONTROL
2016-2017
Challenges:
Turbidity NTE 30% increase
Deep water, significant currents
Buried obstructions precluded sheet pile
Silt curtain not effective enough
Pressing project schedule
Solutions:
Bottom-sealing filter barriers
Designed to perform for the 6-month project schedule, allowing for cost-saving design elements
Responsive to schedule needs
Outcome:
No project exceedances
In-water maintenance allowed performance to continue for an unplanned extension from 6 to 18 months
Bulky underwater debris complications addressed without compromise in performance